The updates introduce changes to the handling of housing conditions disputes. Here we will only focus on the changes that affect Private Rented Sector landlords.
The revised Protocol retains the fundamental objective of resolving disputes wherever possible without litigation, while promoting timely remedial works, appropriate compensation and proportionate costs. The changes warrant careful consideration, particularly where claims involve significant hazards or statutory duties requiring urgent action.
More detailed Letters of Claim
Under the revised Protocol, a tenant’s Letter of Claim should provide sufficient information to enable the landlord to understand the alleged housing conditions and respond appropriately.
Alongside details of the defects, their history and previous notification, the letter should identify whether the tenant considers the situation urgent or an emergency, and explain why.
The tenant should identify whether they believe the property is affected by an emergency or significant hazard under the Regulations, together with the reasons for that belief.
Landlord responses and continuing obligations
The updated Protocol clarifies what is expected of landlords responding to housing conditions claims.
In addition to addressing liability, disclosure, expert evidence and proposed remedial works, landlords are expected to provide information about investigations already undertaken, their outcomes and any further investigations proposed.
Of particular importance is the relationship between the pre-action process and a landlord’s underlying legal obligations.
The revised Protocol expressly recognises that a Letter of Claim may itself constitute notification of poor housing conditions. It also makes clear that participation in the Protocol does not suspend or diminish a landlord’s statutory or contractual duties.
A landlord cannot rely on the pre-action process as justification for delaying investigations, repairs or other legally required action.
This reinforces the importance of ensuring that Letters of Claim are considered promptly.
Greater emphasis on alternative dispute resolution
Alternative dispute resolution (ADR) features more prominently in the updated Protocol.
Parties are encouraged to consider whether disputes can be resolved without court proceedings, including through mediation, complaints procedures or other appropriate mechanisms.
The Protocol recognises that ADR may be pursued at any stage and that the court may require parties to explain whether alternative means of resolution were considered.
The underlying message remains that litigation should ordinarily be a last resort.
However, the emphasis on early resolution must be balanced against the need for urgent intervention where housing conditions present serious risks.
Urgent cases: a more explicit approach
The revised Protocol acknowledges that full compliance with the usual pre-action steps may not be appropriate in every case.
Where there is a serious risk to health or welfare, or where following the ordinary process would conflict with mandatory statutory requirements, urgent court intervention may be justified.
Similarly, the Protocol permits earlier instruction of an expert where urgency requires it, including circumstances involving significant health and safety risks, applications for interim injunctions or the need to preserve evidence.
What remains unchanged?
Although the Protocol has been revised and reorganised, the principal timescales for landlord responses and expert evidence remain in place.
Landlords should normally respond to a Letter of Claim within 20 working days, while the existing framework for single joint experts, joint inspections and the exchange of expert reports continues.
(These procedural timescales must not, however, be confused with the separate and potentially shorter deadlines imposed by Awaab’s Law. Note, Awaab’s Law currently only relevant to the Social Housing Sector. To be introduced in the Private Rented Sector at a later date. That being said, damp and mould issues come under the Housing Health and Safety Rating System hazards, so must be seen as a hazard and dealt with promptly by Private Rented Sector landlords).
The updated Protocol also continues to emphasise that expert evidence should be restricted to what is reasonably required to resolve the dispute.
Preparing for 30 November 2027
The revised Protocol does not fundamentally alter the purpose of the pre-action process. Its significance lies in bringing the procedural framework into closer alignment with developing statutory housing standards, while reinforcing the importance of early engagement, proportionate evidence and timely resolution.
In Summary
- Keep excellent records
- Respond to tenant’s repair issues promptly
- Record findings, carry out works, and have a record of the resolved issue
- Keep communication open, friendly and professional with your tenant
- Carry out regular maintenance checks (with your tenants permission to enter), record findings
- Carry out a Landlord Housing Health and Safety Rating System inspection on your own property, it’s surprising what hazards you may find. Repair and resolve any hazards that are found (use the SWLA document titled ‘HHSRS Tool for Landlord Maintenance Checks’